Location: Chittening Road & Severn Road
Works: Openreach – need access to underground structure
Duration & Dates: 2 days, 14th – 15th February 2022
Times: 09:30-15:30 daily
Works Ref: PS21_521 Severn Rd_Chittening Rd
TM plan: Multi-way portable signals – see maps below