Location: Severn Road (near Seabank Power Station)
Works: Telecoms – Civils Pole Foundation, Cab Bases and Ducting etc
Duration & Dates: 6 days from 21st – 26th February 2022
Times: 24/7 for 6 days (manual control between 07:00-09:30 and 15:30-18:30)
Works Ref: TW21_684 Severn Road
TM plan: Two-way portable signals. See map
