A403 works – Suez roundabout to jnt with Chittening/Severn Rd – 18th Jan to 25th Feb  

Jan 12, 2024 | Uncategorised | 0 comments

2-Way and Multi-Way Signals on Severn Road/Chittening Road

Location: Severn Road (From Suez Roundabout to jct Chittening Road) 

Works: TSG Solutions – Section 50 Electricity Installation Works   

Duration & Dates: 09:30 Thursday 18th January to 15:30 Friday 25th February 

Times: 24 Hours 

Works Ref: PS23_481 Chittening Road

TM plan: 

Two-Way and Multi-Way Signals. These will be manned/manually controlled from 07:00 to 19:00 during the week.

Phases of work

Traffic Management (TM) Phases 20-24 – 2 Weeks (18/01 – 30/01 – Approximately 2-3 days on each TM plan

Traffic Management Phases 25-27  – 2 weeks (31/01 – 15/02)

  • TM Plan 25 – 5 days
  • TM Plan 26 – 3 days
  • TM Plan 27 – 2 days

Traffic Management Phases 28-29 – 2 weeks ( 16/02 – 25/02)

  • TM Plan 28 – 5 days
  • TM Plan 29 – 5 days

Join Us 

We’ve built upon the links developed between businesses, the community, local authorities and other stakeholders over the last 10 years.

Working with over 200 businesses/organisations we have achieved significant results.

Sign up to our newsletter

Sign up here to our e-newsletter to receive our latest news, updates and information about our events