Avonmouth Way Works – by Access 18 – signal controlled works – 29/10/25-17/10/25

Sep 29, 2025 | News, Roadworks, Transport | 0 comments

Following discussions with the contractors and developers these works are now being undertaken via signal controlled traffic management rather than a lengthy closure, should everything go to plan!.

Location: Avonmouth Way 
Works: 2x S50 Foul/Drainage Water connections   
Duration & Dates: 3 weeks, from 29th September – 17th October 
Times: 24/7 from commencement of works 
Works Ref: PS25_022 Avonmouth Way
Traffic Management: Two-way and multi-way lights – see images below

Traffic management in area of Avonmouth Way sub-station

Traffic management around Fourth Way and Access 18 link road

Join Us 

We’ve built upon the links developed between businesses, the community, local authorities and other stakeholders over the last 10 years.

Working with over 200 businesses/organisations we have achieved significant results.

Sign up to our newsletter

Sign up here to our e-newsletter to receive our latest news, updates and information about our events