News Public News Roadworks Transport

M48 cable inspection works running until Jan 2023 – with closure this weekend

National Highways is undertaking a programme of work relating to cable inspection which will run until January 2023. See more details below.M48 Bridge Closure this weekendAs part of this work, there is a need for the M48 Bridge to be closed in both directions from today, Friday 30th September at 19:00 until Monday 3rd October at 06:00.Cable Inspection Works ProgrammeTo carry out these cable inspections and to ensure the safety of both the travelling public and our workforce, long-term lane closures will be put in place. The inspection works will involve the closure of one lane westbound from the 22 June 2022 until around January 2023, and one eastbound starting from July 2022 until around November 2022, with the overall programme of works lasting for around eight months.During the period of lane closures, vehicles over 2.9 metres wide will be prohibited from using the M48 Severn Bridge, and the bridge will also be closed totally over three weekends to enable the lifting of the inspection gantries to a high level on the suspension cable. We will communicate these well in advance. You can keep up to date with the works and read the latest update here: ttps://nationalhighways.co.uk/our-roads/south-west/m48-severn-bridge-suspension-cable-inspections/ M4 Bridge MaintenanceThe M4 Bridge will be closed for maintenance overnight as per the above table:Eastbound –  Mon 3rd Oct at 21:00 to Tues 4th Oct at 06:00Westbound – Mon 10th Oct at 21:00 to Tues 11th Oct at 06:00                        Tue 11th Oct at 22:00 to Weds 12th Oct at 06:00
News Public News Roadworks Transport

M49 Northbound & Southbound Full Overnight Closures – Mon 11th to Sat 16th July

National Highways will shortly be carrying out essential road marking and stud renewal works on the M49.The work will start on the evening of  Monday 11 July and finish on the morning of Saturday 16 July and will take place overnight between the hours of 21:00 and 06:00 on weeknights only.The work is currently programmed as follows: Mon 11 July to Weds 13 JulyFull overnight closure of the M49 southbound for 2 nights from 22:00 until 06:00 the following morning. Weds 13 July to Sat 16 JulyFull overnight closure of the M49 northbound for 3 nights from 22:00 until 06:00 the following morning.There will also be lane closures from 21:00 until 22:00 for the duration of the works. There will be a fully signed diversion route in place during the full overnight closure, but please allow extra time for your journey. If you would like further information about this work, please contact National Highways Customer Contact Centre on 0300 123 5000 open 24/7, who will direct your enquiry to the most appropriate person, or email: info@nationalhighways.co.uk
News Public News Transport

Fuel Protests M4, M5 and M32 – Monday 4 July

Please be aware of the following planned protests this coming Monday 4th July which may impact traffic. You can download a pdf of these notices here. Notice of Planned Demonstration Date4 July 2022Time0700-1900LocationM4 Prince of Wales Severn Bridge.It is unclear if the old Severn Bridge (M48) is also involvedOrganiserNumerous small groups. Gwent Police are leading on consultationPurpose of ProtestProtest at the cost of road fuel.Planned ActivityGwent Police have authorised a demonstration 0700-1400 on the west side of the second Severn crossing, the Prince of Wales Bridge (where the toll booths used to be). Some demonstrators would like to fully blockade the bridge in both directions for this period.Estimated Attendance NumberOrganisers expect 120 to attendLevel of DisruptionDepends. If the bridge is fully closed then this will create serious disruption on M4 and M5. This could then create significant disruption throughout the local area and beyond.Services ImpactedDisruption to the major road networkDisruption to emergency servicesDisruption to council activityBusiness continuity issuesPlanned UpdateMonday 4 July 2022Additional InformationMulti-agency TCG at 0800 Monday 4 July 2022. Gwent Police are leading. The fact that numerous small splinter groups are involved makes consultation difficult.If you have any additional information on this activity, please email Protests@bristol.gov.uk Notice of Planned Demonstration Date4 July 2022Time0845 – 1300LocationM5 Jn24 (Bridgwater) >> M5 Northbound >>M4>>M32OrganiserAvon and Somerset Police are leading on consultationPurpose of ProtestProtest at the cost of road fuel.Planned ActivitySlow moving (30mph) convoy causing traffic disruptionEstimated Attendance Number80Level of DisruptionDelays and slow-moving traffic on the motorway network.Services ImpactedDisruption to the major road networkDisruption to emergency servicesDisruption to council activityBusiness continuity issuesPlanned UpdateMonday 4 July 2022Additional InformationIt is unclear where the protest will end. It is also unclear whether the protesters will attempt another 30mph convoy on the return journey.If you have any additional information on this activity, please email Protests@bristol.gov.uk
Nature News Public News

Sponsor a street tree in the area

Interested in seeing more trees across our industrial landscape and villages? Find out more here. The Bristol – Sponsor a Street Tree scheme enables you to sponsor a tree to be planted in one of over 1,000 pre-approved locations across the city, or pick a location for planting in a grass verge in your street or neighbourhood.
Nature News Public News

Bee Bold Awards

West of England Combined Authority Mayor Dan Norris visits sites in the area to promote the Bee Bold awards for 2022. Pictured with the GenEco team at the sewage treatment works in Avonmouth. May 2022. Celebrating organisations taking action to support pollinators and tackle the ecological crisis. We want the West of England to be the Bee and Pollinator Capital of the UK. West of England Metro Mayor Dan Norris has launched the region’s first Bee Bold Awards to recognise organisations big and small that are taking positive action to support bees and pollinators. Find out more here.Watch a short video here featuring the meadow(s) created at the Bristol Waste Treatment Plant off Kings Weston Lane.
Energy News Public News

Hinkley Connection Project Update

The Hinkley Connection Project is progressing. National Grid: “In April 2022, we completed building the new pylons and overhead connection along the southern part of the route between Bridgwater and Loxton.In July 2022, we will start building the remaining overhead connection from Sandford to Seabank, near Avonmouth.We’re using the new T-pylons for part of the route between Sandford and Portishead, and new traditional lattice pylons through Avonmouth to make the final connection into Seabank substation.We will continue to directly contact the businesses close to where our work is being carried out to coordinate our construction activities.” You can find some great pictures and video here of the the world’s first T-pylon being built in Somerset. Work is progressing around Crook’s Marsh with the profiling of the land and the stone deliveries Have strated to ramp up. All vehicles working on behalf of the Hinkley Connection Project display the project identifier below. If you have any concerns please let us know via email.
Community Economy Events News Public News Strategic Planning Transport

Join us at July’s Business Breakfast featuring the 5G logistics trials and Severnside Masterplan

Date and Time: Th. July 21st – 07:30-09:00Host: The Bristol Port CompanyWhere: The Bristol Port Safety & Training Centre, St. Andrew’s House, St. Andrew’s Rd., Avonmouth. BS11 9DQ Please join us to hear about the 5G logistics trials that took place at the Port and locally in May, including improvements to the lights at the junction of St. Andrew’s Rd and Kings Weston Lane; and a presentation and a chance to discuss the Vision for Severnside being developed by S. Glos. Council with communities of interest. Book here to come along and join us on the 21st
Community Economy News Public News Strategic Planning Transport

A Vision for Severnside – Severnside Masterplan. We encourage you to take a look and comment

South Glos. Council is working with the local community, town and parish councils, and businesses, on a strategic infrastructure led masterplan for Severnside.The aim of the masterplan is to develop a locally informed vision to help shape the future of Severnside in the medium and long term, up to 2050. It will build on all of the different strengths that the area has. The plan is now in its public engagement phase and we encourage you to take a look and comment before the 24th July 2022. The website is here. You can also download a pdf of the exhibition boards here (3Mb). This Vision for Severnside will be presented and discussed at the July Business breakfast which will be held at The Bristol Port Company’s Safety and Training Centre in St. Andrew’s House, Avonmouth on Th. July 21st. Come and join us. Book here.
News Public News Roadworks Transport

M48 Severn Bridge cable inspection works closure weekend from Fri eve 1st July 2022

Update from National Highways”Unfortunately, weather conditions last weekend while we had the M48 bridge closed (25 and 26 June) meant we weren’t able to complete all the necessary works to lift the gantries into place on the support trestles, as it wouldn’t have been safe to do so. As such, weather permitting, a further full closure of the M48 Severn Bridge will be taking place this weekend, from 7pm on Friday 1 July until 6am on Monday 4 July. During the full closure, diversion routes will be in place across the M4 Prince of Wales bridge. The eastbound foot and cycle path will remain open. We weren’t able to safely complete the crane lifting operations to move the gantry platforms from the lorries on the carriageway onto the support trestles due to high winds during the closure. We did however make some good progress, including the installation of gantry support trestles and temporary barriers on the westbound carriageway, removal of redundant electrical cables on the suspension cable at areas critical to the project and removal of lighting columns in close proximity to gantry access platforms. Keep up to date with the works You can keep up to date with the works and read the latest update here:  Getting in touch with National Highways If you would like more information about this work, please contact the National Highways Customer Contact Centre on 0300 123 5000 open 24/7, who will direct your enquiry to the most appropriate person, or email: info@highwaysengland.co.uk  For information on all of our works in the South West please follow us on Twitter @HighwaysSWEST” 13/6/22 – M48 Severn Bridge cable inspection works starting 22nd June 2022 until Jan 2023 In order to ensure that structures on the Strategic Road Network in England are kept in good condition and remain safe for the public who use them, National Highways need to conduct regular checks to monitor how they are performing and repair any damage that is found. One of these structures is the Severn Bridge carrying the M48 over the River Severn, where we are required to inspect the suspension cables.To carry out these cable inspections and to ensure the safety of both the travelling public and our workforce, long-term lane closures will be put in place. The inspection works will involve the closure of one lane westbound from the 22 June 2022 until around January 2023, and one eastbound starting from July 2022 until around November 2022, with the overall programme of works lasting for around eight months. During the period of lane closures, vehicles over 2.9 metres wide will be prohibited from using the M48 Severn Bridge, and the bridge will also be closed totally over three weekends to enable the lifting of the inspection gantries to a high level on the suspension cable. We will communicate these well in advance. The first full closure is planned for the weekend of 25 and 26 June, with motorists being diverted across the M4 Prince of Wales Bridge. To minimise any future disruption, maintenance work will also be undertaken during the closures, including refurbishment and maintenance of many bridge expansion joints, carriageway surfacing repairs, reinstatement of some under bridge gantry bogies and wheels, sweeping and litter picking, blasting and painting of parapets and lighting column bases, weld repairs, carriageway inspections, and gulley and drain cleaning.The full details and press release can be found here.To follow the progress of the works and to keep up to date, please visit this webpage.National Highways “We will make every effort to ensure the impact on the local community and travelling public is kept to a minimum. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes to it.”If you would like more information about this work, please contact the National Highways Customer Contact Centre on 0300 123 5000 open 24/7, who will direct your enquiry to the most appropriate person, or email.For information on all of our works in the South West please follow us on Twitter @HighwaysSWEST